Client
Jernbaneverket Utbygging
(Norwegian National Rail Administration)
Construction Period
04.2011 – 03.2015
Contract Sum
CHF 68 Mio. (NOK 414 Mio.)
Joint Venture Company
Marti ÍAV DA
Joint Venture Partners
Marti Tunnel AG, CH-3302 Moosseedorf
ÍAV hf, IS-110 Reykjavik
Lead Company and Technical Lead
Marti Tunnel AG, CH-3302 Moosseedorf
Commercial Lead
ÍAV hf, IS-110 Reykjavik
More…
Less…
Project description
The UHN 07 Snekkesatd project is the southernmost
2.5 km long construction lot of the double track railway
line between Holm and Nykirke, which aims to modern-
ize the Vestfold railway system. The main parts of the
project consist of:
- 2’100 m long (135 m²) double track railway tunnel
- 400 m of double track railway
- 320 m long (53 m²) adit/escape tunnel
- 380 m long (24 m²) escape tunnel
Work description
Underground excavation, rock support and grouting work
- Excavation methods: drill & blast, pipe umbrella
advance (60 m)
- Excavated length and volume: 2’995 m, 332’000 m³
- Grouting method: systematic cementous pre-grouting
- Grouting quantity: 208 rounds, 10’000 t of cement
- Standard rock support: shotcrete (9’930 m³) and
systematic rock bolts (19’600 pcs)
- Additional rock support: reinforced shotcrete arches
(36 pcs.), steel beams (57 pcs.)
Underground water and frost protection work
- Concrete elements lining: 51’350 m²
- PE-foam & shotcrete lining: 12’360 m²
- Spray applied membrane & shotcrete lining: 2’700 m²
Surface- and groundwork
- Sheet piling work in the portal area
- Roadwork
- Fresh water and drainage system
- Installation of cables pipes and channeling
Concrete work
- 3 technical buildings
- One 50 m long portal
Electrical work